Thursday, September 28, 2017

3rd Avenue September 2017 updated.

i visit 3rd Avenue site.here is the photos taken at the site. progress smoothly.

Thursday, September 7, 2017

3rd Avenue August 2017 updated.

this is contruction updated on end of August 2017.

3rd avenue stop work from April to Jun 2017

3rd Avenue stop work from April 2017 to
Jun 2017.
it due to the developer and main contractors payment issue.
The construction resume back on July 2017.
Hope construction progress smoothly after this stop work.

Saturday, April 8, 2017

Saturday, March 11, 2017

3rd avenue March 2017 update

Visit Cyberjaya again this weekend.
Send my son to the rero robotic class.
Take latest photo for 3rd Avenue.

Friday, March 3, 2017

King Henry VIII College@ Cyberjaya

At the ground-breaking ceremony for the King Henry VIII College together with Acting British Deputy High Commissioner to Malaysia Paul Rennie in Cyberjaya yesterday. King Henry VIII College in Cyberjaya is the first overseas college of the Christ College Brecon; one of the oldest and most successful independent schools in the UK. 1st of march 2017.

Saturday, February 18, 2017

3rd avenue February 20170 updated.

first visit 3rd avenue after CNY 2017.
the progress look good.
Glass window start to install at the office building.
Tower one start painting.

Thursday, February 9, 2017

MEX 2 start construction at January 2017

MEX highway  2 from kl to klia start construction now.
it will shorten the time to klia by 20 minite.
This highway will pass by 3rd avenue.

Reports indicate that work has begun on clearing land parcels around the Putrajaya toll plaza area to facilitate the start of the Lebuhraya Putrajaya – KLIA (MEX II) expressway extension project.

The new expressway plans to provide the shortest and most direct route between the KL city centre to the KLIA and KLIA 2 when linked to the existing 26 km-long MEX, which was completed in 2007. Originally, it was reported last year that tolling operations for the new extension were slated to commence in November 2018, but a date of completion has yet to be announced.

When ready, the open-toll, three-lane dual carriageway will be 18 km-long and will provide a mainline connection between the existing Lebuhraya Maju Expressway (MEX, or E20) to Lebuhraya KLIA (FT26). The route will commence at Putrajaya Interchange and merge onto the FT26 in Sepang.

Aside from the usual entry and exit ramps to and from the expressway, there will be 26 bridges along the route, and MEX II will feature one mainline toll plaza, two ramp toll plazas and a supervision building.

Saturday, January 14, 2017

Cyberjaya convention hall

convention centre at cyberjaya.
Built by MRCB.
Target completed at 2020.

“The master plan is already in place but the actual type of products and pricing will be determined later. Right now the focus is to kick-start Phase 1 and complete the convention centre in time for the World Congress of Information Technology 2020.


Thursday, January 12, 2017

3rd Avenue January 2017 updated.

Here is latest construction progress for January 2017. It up to 25floors already.
Good progress.